Week Day Start End Time Activity Description
1 1/11/2008 9:30 pm 12:30 am 3 hr BrainStorm / Bids Project ideas / create bids
2 1/13/2008 9:30 pm 10:30 am 1 hr Research Finding and Setting up SCRUM tool
2 1/18/2008 2:30 pm 4:30 pm 2 hr Meeting with Daz3D - Sponsor Discuss and plan project with daz
3 1/23/2008 8:00 pm 11:00 pm 3 hr Environment Setup Got Enviroment setup with dll compling and SDK
3 1/26/2008 12:00 pm 3:00 apm 3 hr Daz Technical Training Ran Through the DAZ technical training and worked on setting up a plugin using the sdk
3 1/27/2008 12:00 pm 1:00 pm 1 hr Website Update Updated Log etc
4 2/2 5:00 pm 8:00 pm 3h Development Sprint 1 development
5 2/4 5:30 pm 9:00 pm 3h 30m Development Sprint 1 & 2 development
5 2/6 5:30 pm 10:30 pm 5h Development Wrap up Sprint 1 development
5 2/7 7:30 pm 9:30 pm 2h Documents SDS Document v1 (and 2)
6 2/11 8:30 pm 10:30 pm 2h Documents SDS Document v1 (and 2)
6 2/15 8:30 pm 9:30 pm 1h Documents SDS Document v1 (and 2)
6 2/16 10:30 pm 12:30 pm 1h Website Update Update Logs and SDS V1
7 2/20 7:30 pm 8:30 pm 1h Sponsor Resolve project plans
7 2/21 11:30 am 12:30 pm 1h Sponsor Resolve project plans
7 2/24 9:30 pm 10:00 pm 30m Team Meeting Discuss project's future
7 2/24 10:30 pm 11:50 pm 1h Setup/Research Researched / Installed Online Scrum Tool
8 2/26 15:00 pm 6:30 pm 1h 30m Setup Configured Online Scrum Tool / Added Tasks
8 3/1 6:00 pm 7:30 pm 1h 30m DazStudio Make list of desired enhancements
8 3/2 11:30 pm 12:30 Am 1h Website WMR / update log
9 - - - 5hr Work / Documentation Work On Enhancements
10 3/14/2008 9:00 pm 11:00 pm 2 hr Work / Documentation Test for release / VVR documentation
11 3/17/2008 8:00 pm 11:00 pm 3 hr Work / Documentation 3d Pane Planning / Implementation
11 3/19/2008 7:00 pm 10:00 pm 3 hr Work / Documentation 3d pane Implementation / Testing
11 3/20/2008 9:00 pm 10:00 pm 1 hr Work / Documentation Testing
12 3/25/2008 9:00 pm 12:00 pm 3 hr Work Implementation of Scale / Rotate
12 3/27/2008 7:00 pm 10:00 pm 4 hr Work / Testing Implementatino / Testing for Scale/Rotate Functionality
14 4/8 7:00 pm 10:00 pm 3h Development Enhancements / Bug Fixes
14 4/11 9:00 pm 12:00 am 3h Documents Testing / VVR 3 / Brochure
14 4/13 10:00 pm 10:30 pm 30m Website Update logs / WMR/ Brohure