Accomplishments:
  • This week we had a formal meeting with DAZ: Brandon, Travis, Tony
    • We fine-tuned what the project will be and how it will be carried out.
    • We created a second revision of our bid to fit the modification that came about during our meeting.


Priorities:
  1. Meet with DAZ to finalize project plans: Entire Team
  2. Get our development environments set up: Entire Team
  3. Begin development: Entire Team
  4. Begin writing Project Plan: Entire Team


Needs:
Tom: Any remaining details about making our sponsor official.
Daz: Another meeting with more specific project details.