cs4500 Weekly Management Report
week three: January 28, 2008
Accomplishments:
- Project meeting with DAZ: Brandon, Travis
- General project plan discussion for first sprint
- Coordinated work schedules for project
- Development Environment Setup
- Worked out wrinkles with configuration setup with our tech lead: Brandon
- Setup our own personal environments for remote use: Brandon, Travis, Tony
- Daz Technical Training: Brandon, Travis
- Review SDK documention, and QT(crossplatform framerwork) API
- Build Daz Studio plugin according to training specs.
- Updated website: Brandon, Travis
Priorities:
| # | Description: | Responsible: | Due Date: |
| 1 | Development Sprint 1 | Entire Team | 2/11/08 |
| 2 | Project Plan for Sprint 1 | Travis | 1/31/08 |
| 3 | SRS V1 | Brandon | 2/5/08 |
| 4 | SDS V1 | Tony | 2/8/08 |
Needs:
Tom: Any remaining details about making our sponsor official.
Daz: Sprint 1 - Implementation Task list (Need by 1/28/08)