Team BLT
cs4500 Weekly Management Report
week four: February 4, 2008

Accomplishments:
  • Get setup at DAZ: Brandon, Travis, Tony
    • Get computers setup with email, source, etc.
    • Get hr paperwork stuff taken care of
  • Get Development under way
    • Start work on pane dragging: Brandon
    • Start working on gui handle problems: Tony
    • Start working on refreshing display when resizing areas: Travis
  • Sprint 1 Project Plan
    • Complete the project plan for the first sprint: Travis
  • Updated website: Brandon, Travis


Priorities:
# Description: Responsible: Due Date:
1 Development Sprint 1 Brandon - panes, Tony and Travis - help with panes, then move on to sprint 2 tasks 2/6/08
2 SRS V1 Brandon 2/5/08
3 SDS V1 Tony 2/8/08


Needs:
Tom: Nothing this week
Daz: Sprint 2 - Implementation Task list (Need after our sprint 1 is reviewed, probably thursday.)